According to the new design costs no longer reside in the Route asset...Instead it will get distributed to the member Assets, even if you have a work order for the Route asset.
For the example :
If you have a work order, Route asset Costs for this work order will get distributed to the member assets for the route, When you look at Work Order Value Summary form, you look at costs for a particular work order...Hence in the work order value summary form, you are able to see the costs for the work order
However in Self Service, According to the new design the Route asset would not hold any cost..It will get distributed to its member Assets..Hence Route asset does not show up any cost ,However if you search for costs for each of the member Assets, then you will be able to track the cost of the work order for the Route asset
Asset route is a logical asset and costing of asset route works as below:
During the transaction processing, costs are accumulated to the A/c's in the Asset route work order WIP accounting class. Till the closure of asset route work order , these costs would be accounted in the WIP of Route work order only.After closing the Asset route work order, these costs would then be actually distributed to each of the member asset "WIP accounting class variance accounts"
No comments:
Post a Comment